Line: 27 to 27
 
  • Test runs on Hartee systems for iterative methods continue but can require about 20hrs/iteration. The code has been modified to reduce memory requirements for workstations and the next stage is looking at alternative technologies.
  • A dedicated CCPi YouTube? channel continues to be exploited:http://www.youtube.com/channel/UCGB578xcyXNQyiBsufEFIeQ
  • Added two new iterative reconstruction algorithms from network members and flagship project and on the CCPForge.
Changed:
<
<

Metrics 2013/4 need values for 2014/5

>
>

Metrics for 2014/5

 
Changed:
<
<
Highlights during the financial year 2013/4:
>
>
Highlights during the financial year 2014/5:
 
  • STFC staff have been no direct publications but a set of papers are in preparation
  • STFC staff have given some 7 presentations at meetings ranging from formal site visits (four developers' day site visit presentations) to three invited talks at conferences and exhibition meetings (including KTN etc).
Changed:
<
<
  • There has been one main publication (Daniil Kazantsev et al 2014 Inverse Problems 30 065004. doi:10.1088/0266-5611/30/6/065004) that reference codes developed through the SLA and two in press plus special issue on Phil Trans.
  • Over 10 training courses there were 33 training days covering PhD supervision, code workshops and scientific meetings. Average attendance was 12 and approximately a quarter were directly of indirectly PhD students (approx 100 PhD student days of training).
>
>
  • There has been one main publication (Daniil Kazantsev et al 2014 Inverse Problems 30 065004. doi:10.1088/0266-5611/30/6/065004) that reference codes developed through the SLA and others in press
  • Over 10 training courses there were 18 training days covering PhD supervision, code workshops and scientific meetings. Average attendance was 12 and approximately a quarter were directly of indirectly PhD students (approx 54 PhD student days of training).
  April 2014 - March 2015
Line: 97 to 97
 
  • Creation and maintenance of test-cases of PET/MR data and reconstructions - Q4 2015 and release Q1 2016
  • Profiling and (if necessary initial speed-up) of 1 PET and 1 MR image reconstruction package - Q3 2015 and Q1 2016
Changed:
<
<
Task Effort
>
>
Task Effort 2015-2016
 
  • Secretariat Coordination for both CCPs 0.2
  • Basic maintaining network, website, organising administration for workshops and training courses, (Core SLA activities allocation) 0.14
Line: 107 to 107
  Total 2.6 FTEs
Changed:
<
<
Staffing Effort
>
>
Staffing Effort 2015-2016
 
  • Group Leader - Martin Turner 0.50
  • Barry Searle 0.17
 